As part of the Severn Bridge project, Bill Brown and the Freeman Fox team worked on a separate bridge and viaduct over the River Wye. This shorter, four-lane road crossing acted as a continuation of the main Severn Bridge and the M4 motorway. It became the M48 motorway when the Second Severn Bridge opened in 1996.
Bill had shown that, by getting the shaping and stiffened plates right on this project, he could produce a suspended structure that was up to 25% lighter than a more traditionally constructed crossing. It was a similar welded box to the main structure and indeed its design phase had influenced the decision to use a box girder deck on the main Severn superstructure.
Wye Bridge
Linking South Wales and England
Key Facts
Cable-stayed suspension bridge
Part of the Severn Bridge project
Advanced box girder deck
Location
Monmouthshire, Wales
Across the River Wye
Linking Wales and England
Consulting Engineers
Freeman Fox & Partners
Description
Cable-stayed Suspension Bridge
235m main span
1,153m total length
Main contractors
Cleveland Bridge & Engineering Co. Ltd.
Construction
Opened 1966
Crossing the Beachley Peninsula
The viaduct connecting the Wye Bridge to the Severn Bridge took the entire crossing right over the Beachley Peninsula near Chepstow. The Wye Bridge was constructed of steel with reinforced concrete piers. Its main span was 235 metres long and its road deck consisted of a continuous steel box girder measuring 14.6 metres wide.